Schedule

13/03/2016 Initial sales meeting with Clarendon @ Parklea
17/03/2016 Initial Deposit paid
27/04/2016 Tender appointment
9/05/2016 Tender Deposit paid
24/05/2016 Contract Appointment
1/06/2016 Contract Deposit paid
18/06/2016 Austral Bricks open
21/06/2016 Colour Appointment
22/06/2016 Smart home and Electrical appointment
16/07/2016 Tile selection
10/08/2016 CDC Approved
6/09/2016 Demolition started
14/09/2016 Demolition Complete
23/09/2016 Final Drawings signed off
27/09/2016 In Construction
28/09/2016 Site Cut
11/10/2016 Slab Poured
19/10/2016 Drainage around the house
16/10/2016 Frame work started
28/11/2016 Plumbing roughing
2/12/2016 Bricks Started